Introduction
With the VCF 9 management domain up and running, the next step in your private cloud journey is creating workload domains. A workload domain groups ESX hosts under a dedicated vCenter instance, along with NSX networking and storage, so it can host tenant or departmental workloads. Depending on how you configure NSX connectivity during creation, a workload domain can become VPC-ready either immediately or after a short follow-up step: more on that below.
Three Ways to Create a Workload Domain
Per VCF Operations’ Workload Domain wizard, there are three supported paths:
- Full deployment with cluster: deploys a fully provisioned workload domain with an initial vSphere cluster. Requires ESX hosts already commissioned with the target principal storage type.
- Domain infrastructure only: deploys and configures a new vCenter instance and a new-or-shared NSX Manager instance, without requiring any unassigned ESX hosts. You add a vSphere cluster to it later.
- Import an existing vCenter: brings an already-running vCenter and its managed ESX hosts under VCF as a workload domain, so it’s included in centralized identity, certificate, and lifecycle management.
Architectural Overview
The diagram below illustrates the relationship between the VCF 9 management domain, VCF Operations, and multiple workload domains, including VPC-based networking topology:
Workload Domain Planning Considerations
Before creating a workload domain in VCF 9, use the VCF Planning and Preparation Workbook to document all design decisions. Key areas to plan:
Compute Sizing
- Minimum of 3 ESX hosts for a vSAN ESA workload domain
- Size CPU and RAM based on the expected VM density and workload type (compute-intensive, memory-intensive, or mixed)
- Account for ESX host management overhead and vSAN overhead when calculating usable capacity
- For high availability, plan for N+1 host capacity so one host can fail without a performance hit
Storage Design
A workload domain can be built on one of four principal storage types, selected during the wizard’s Storage step:
- vSAN: either ESA (the current recommended architecture) or OSA; requires SSD or NVMe disks free of pre-existing partitions
- NFS: an external NFS datastore, identified by server IP and export path
- VMFS on FC: Fibre Channel-backed VMFS datastore
- vVols: supported for compatibility, but Broadcom has marked vVols as deprecated as of VCF/vSphere Foundation 9.0, with removal planned in a future release; new designs should avoid it
Networking Design
| Network Segment | Purpose | Configuration Notes |
|---|---|---|
| Management VLAN | ESX management, vCenter | Must be reachable from VCF Operations |
| vMotion VLAN | Live VM migration | Dedicated VLAN for performance isolation |
| vSAN VLAN | Storage traffic | Dedicated VLAN, jumbo frames recommended |
| NSX Overlay (Host TEP) | Tenant Geneve-encapsulated traffic | Needs a static IP pool or DHCP scope |
| NSX Edge Uplink | North-south routing to physical network | Dedicated VLANs for T0 connectivity |
NSX and VPC Planning
Every workload domain needs an NSX Manager, which can either be a new dedicated instance or a shared instance already used by another domain (subject to version-compatibility rules between the shared NSX Manager and each domain’s vCenter version). When configuring VPC Gateway Connectivity during creation, you choose between:
- Centralized Connectivity: simpler to set up, but the domain becomes VPC-ready only after you separately deploy an NSX Edge cluster with a Tier-0 gateway afterward
- Distributed Connectivity: requires a dedicated VLAN, gateway CIDR, and external/private IP blocks up front, but the workload domain is VPC-ready immediately after creation
Deploying a Workload Domain via VCF Operations
Step 1: Commission ESX Hosts
Before creating a full-deployment workload domain, commission the target ESX hosts (skip this if you’re using the “domain infrastructure only” or “import existing vCenter” paths):
- In VCF Operations, commission hosts with the correct target principal storage type
- VCF Operations validates host connectivity, DNS, NTP, and hardware compliance
- Hosts move to an unassigned state once commissioned, ready to be selected during workload domain creation
Step 2: Create the Workload Domain
- In VCF Operations, click Operate in the top navigation bar, then in the left pane select Overview → Inventory
- Expand VCF Instances and select the instance where you’re creating the domain
- From the Add workload domain drop-down, choose Create new, review prerequisites, and proceed
- Work through the wizard: General Information → vCenter → Cluster → Image → Networking (NSX) → Storage → Hosts → vSphere Distributed Switch → vSphere Supervisor (optional) → Finish
- VCF Operations performs pre-deployment validation, then orchestrates the full domain bringup
- Track progress under Fleet Management → Tasks
Step 3: Post-Creation VPC Setup
If you chose Centralized Connectivity, complete VPC-readiness by deploying an NSX Edge cluster with an active-standby Tier-0 gateway. If you chose Distributed Connectivity, the domain is already VPC-ready: proceed straight to creating VPCs, subnets, and Transit Gateway connectivity for each tenant or application team.
Day-2 Workload Domain Operations
VCF Operations provides built-in automation for common Day-2 operations, and VCF 9.1 adds guardrails so that certain out-of-band changes (made outside the VCF Operations UI, such as expanding a cluster or changing primary storage directly in vCenter) no longer create unresolvable configuration drift:
- Cluster expansion/contraction: Add or remove ESX hosts from an existing cluster via VCF Operations
- Host remediation: Apply ESX updates, patches, or desired-state images across the cluster using vSphere Lifecycle Manager images
- Certificate rotation: Automate certificate lifecycle for all workload domain components from VCF Operations
- License management: Track and submit VCF and vSAN license usage periodically directly from VCF Operations
Sources
Validated against Broadcom’s official VCF 9.1 documentation: Building Cloud Infrastructure, Managing VCF Domains, and Create a New Workload Domain.
What’s Next
In the next post, we will do a deep dive into VCF 9 NSX VPC networking, covering Transit Gateway design, VPC consumption from vCenter, and practical examples of deploying application workloads using VPC-based isolation.